PH Haiyan Seeks Complete Records on ₱216.7 Million COA Findings in Tacloban City
Official Correspondence Nov 10, 2026
Story-backed public record

PH Haiyan Seeks Complete Records on ₱216.7 Million COA Findings in Tacloban City

COA Audit Findings / Public Funds / Transparency and Accountability

PH Haiyan Advocacy, Inc. continues to seek clarification and supporting documents from the Tacloban City Government concerning ₱216.7 million in findings identified in the Commission on Audit (COA) CY 2024 Annual Audit Report. These involve ₱145.69 million associated with 33 unimplemented development infrastructure projects and ₱70.99 million in unutilized continuing disaster fund appropriations. Following the City Government's response, PH Haiyan submitted a follow-up letter on October 30, 2026, requesting complete documentation, verification of reported project accomplishments, and clarification on the utilization of public funds.

At a Glance
Category
Official Correspondence
Issue Area
COA Audit Findings / Public Funds / Transparency and Accountability
Published
November 10, 2026
Available Files
6 record files
Record Narrative Context, chronology, and public-interest details preserved in a fuller article flow

₱𝟮𝟭𝟲.𝟳 𝗠𝗜𝗟𝗟𝗜𝗢𝗡 𝗖𝗢𝗔 𝗙𝗜𝗡𝗗𝗜𝗡𝗚𝗦 𝗖𝗬 𝟮𝟬𝟮𝟰 𝗦𝗔 𝗧𝗔𝗖𝗟𝗢𝗕𝗔𝗡 𝗦𝗨𝗠𝗔𝗚𝗢𝗧 𝗔𝗡𝗚 𝗖𝗜𝗧𝗬 𝗚𝗢𝗩𝗘𝗥𝗡𝗠𝗘𝗡𝗧, 𝗣𝗘𝗥𝗢 𝗞𝗨𝗟𝗔𝗡𝗚 𝗣𝗔 𝗔𝗡𝗚 𝗗𝗘𝗧𝗔𝗟𝗬𝗘!

Ayon sa Commission on Audit (COA) CY 2024 findings, may ₱145.69 milyon na inilaan para sa 33 sa 37 infrastructure projects na hindi naipatupad noong 2024, at ₱70.99 milyon na disaster funds mula 2023 at mga naunang taon na naitalang hindi nagamit noong 2024.

Noong Oktubre 27, 2026, nagbigay ng ulat ang City Engineer's Office tungkol sa 37 proyekto. Ayon dito, 32 ang iniulat na natapos, isa ang 100% accomplished ngunit may kailangang ayusin, dalawa ang ginagawa pa, at dalawa ang nakansela.

Kinikilala ng PH Haiyan ang tugon. Gayunman, walang kalakip na mga hiniling na sertipikadong dokumento at hindi nakasaad ang mga petsa ng pagsisimula, aktuwal na pagkumpleto, at pagtanggap sa mga proyektong iniulat na natapos.

Kaya noong Oktubre 30, 2026, muling sumulat ang PH Haiyan sa City Government upang humingi ng kumpletong rekord at sagot sa mga sumusunod:
1. Kailan nagsimula at natapos ang mga proyekto? Nasaan ang mga dokumentong nagpapatunay na nasuri at tinanggap ang mga ito?
2. Magkano ang aktuwal na ginastos at natira sa bawat proyekto? Ano ang saklaw at halaga ng mga proyektong tinukoy sa dalawang ulat?
3. Ano na ang kalagayan ng ₱70.99 milyong disaster funds? Nagamit na ba ang mga ito, at para saan?
4. Ano ang naging aksyon sa mga naantala, kailangang ayusin, at nakanselang proyekto?
5. Naipasa ba ang mga kinakailangang ulat sa City Council? Ano na ang estado ng drainage at flood-control plan at koordinasyon sa DPWH?

Nananawagan ang PH Haiyan sa Tacloban City Government na ibigay ang kumpletong sertipikadong rekord at malinaw na paliwanag, upang matiyak ang tunay na estado ng mga proyekto at kung paano ginamit ang pondo.

Karapatan ng mga Taclobanon na malaman kung saan napunta ang kaban ng bayan at kung napakinabangan nila ang mga proyektong inilaan para sa kanila.

TRANSPARENCY AND ACCOUNTABILITY ARE A MUST.

DISCLAIMER: Ang ₱216.7 milyon ay batay sa COA CY 2024 findings sa mga proyektong hindi naipatupad at disaster funds na hindi nagamit noong panahong saklaw ng ulat. Hindi ito nangangahulugang nawawala o napatunayang nagamit sa maling paraan ang pondo. Ang mga iniulat na natapos na proyekto ay batay sa tugon ng City Engineer's Office at hinihingan pa ng dokumentaryong beripikasyon. Layunin ng PH Haiyan ang paglilinaw at transparency sa interes ng publiko.

Related Letters

Continue through connected public records.

These records are tied to the same issue area or advocacy theme.

Official Correspondence Oct 23, 2026

PH Haiyan Seeks Clarification on ₱300.86 Million COA Findings in Tacloban City for CY 2025

COA Audit Findings, Government Transparency and Public Accountability

PH Haiyan Advocacy, Inc. raises concerns regarding the Commission on Audit (COA) findings for Tacloban City, CY 2025, involving ₱300.86 million in project contract costs and appropriations. The findings cover 27 incomplete infrastructure projects worth ₱266.75 million and 8 unimplemented projects with appropriations totaling ₱34.11 million. The report also indicates a 19.59% utilization rate for the Local Disaster Risk Reduction and Management Fund (LDRRMF). PH Haiyan seeks transparency, updated project status reports, supporting documentation, and clear explanations concerning the implementation of public projects and utilization of government funds. These findings reflect conditions as of December 31, 2025, and do not establish that public funds were missing or misused.

Public Accountability Oct 16, 2026

₱216.7 Million Nga Pondo Ha Tacloban: Ano Na An Nahitabo?

COA Audit Findings, Development Projects & Disaster Funds

PH Haiyan Advocacy, Inc. raises public concern over the Commission on Audit’s (COA) CY 2024 findings involving approximately ₱216.7 million in Tacloban City appropriations, covering 33 unimplemented development infrastructure projects and unutilized continuing disaster fund appropriations. Through its public information campaign and formal letters dated October 8, 2026, addressed to the City Mayor and Vice Mayor, PH Haiyan seeks updated project status reports, certified financial records, and clarification on the utilization of these funds to promote transparency, accountability, and the delivery of public services to Tacloban residents.

Infrastructure and Public Accountability Oct 05, 2026

Tacloban Causeway Project: PH Haiyan's Continuing Advocacy for Transparency and Accountability

Tacloban Causeway – Project Completion, Public Funds, Environmental Compliance, and Public Consultation

Since 2025, PH Haiyan Advocacy, Inc. has actively engaged the Department of Public Works and Highways (DPWH), DENR-Environmental Management Bureau, and other concerned government agencies regarding the Tacloban Causeway Project in Cancabato Bay. Through a series of formal letters, information requests, and follow-ups, PH Haiyan has sought transparency on the project's construction status, delays, terminated contracts, utilization of public funds, project redesign, and environmental compliance. The organization has also called for independent verification of completed works, protection of Cancabato Bay, meaningful public consultation, and a clear government action plan for the project's responsible completion. PH Haiyan supports the completion of the Tacloban Causeway, provided that it follows proper procedures, meets environmental and engineering requirements, ensures accountability for public funds, and serves the long-term interests of Taclobanons and the wider Eastern Visayas community.